2012-08-13T09:00:05Z | 2012-08-13T09:00:05Z | 2007-04

The project's objectives were to (i) increase the efficiency and sustainability of Ethiopia's power sector and to increase electricity use for economic growth and improved quality of life; and (ii) improve the utilization efficiency of rural renewable energy. An IDA credit of US$ 200 million over the years 1998-2005 supported these objectives. The project had 3 components: (i) the Gilgel Gibe Hydroelectric plant; (ii) Rural energy; and (iii) Institutional Development. An Emergency Recovery Project was included in June 2004 for emergency equipment and materials for war-affected areas and in particular to replace stranded goods and equipment at Assab Port.